The works mainly included the following activities: erection of access scaffolding, removal of the frontal façade of the building from the ground floor to the second floor, removal of all existing fenestration, construction of a new frontal façade incorporating facing brick and rendered panels, the stripping off of all existing roof coverings, erection of a new steel framed structure to provide additional accommodation at third floor level and the installation of aluminium PPC windows, doors and curtain walling to the required elevations
On completion of the above works, the building was handed over to the Client for further development.